but AI datacenters do not actually use that much energy compared to other industries,
To counter that statement:
The state that made itself America's data center capital just realized the data centers want more electricity than five entire Texases could ever produce. Less than a year ago, Governor Greg Abbott declared Texas the epicenter of AI development. On August 3, 2026, he froze all new data center power connections to the Texas grid and called for a full audit of every project in the queue. The reason was a number so large it barely feels real. ERCOT is currently tracking more than 1,800 projects in the queue, representing over 474 gigawatts of electricity, or more than five times the grid's record for peak demand. Approximately 90 percent of the new power requests are data centers. To put that in perspective, Texas set its all-time electricity demand record in August 2023 at approximately 85.5 gigawatts, during one of the most brutal heat waves in state history.